Ashdown Update
November 21, 2008
The Ashdown mine was placed on care-and-maintenance following the drop in worldwide demand for molybdenum oxide during the past 30 days. With prices for moly falling below $10 per pound, the Management Committee directed the mine and mill staff to immediately put into place a reduction in force as of last week. A member of the Committee has been on site to direct the operations, and equipment and supplies are being secured, supervisory agencies and vendors notified, and security measures inacted in order to maintain the infrastructure and await the outcome of future pricing moves. The mine remains on stand-by status, with permits in place.
August 8, 2008
The Ashdown Mine has resumed production after a successful summer maintenance turnaround. Maintenance in the mine focused on rehabilitation of 150 feet of ground support in the main decline. Utilities were restored including air, water and ventilation. All pumps and water lines were placed back in service. Phone lines were checked and repaired. Sumps were pumped down and mucked out.

Road to new secondary portal & escape way
A second portal into the mine was also completed to serve as a secondary escape way. Timber sets were removed and the ground supported with shotcrete. The #1 raise was cleared of rock and debris. All ladders were installed. Escape way signs installed and maps updated and posted. This portal will provide a needed secondary travel way and an improved ventilation air course.
Maintenance crews at the mill completed repair and replacement of the ball mill lining, two concentrate feed augers and numerous other repairs. During this time period our contractor completed a new trailer park that will provide needed housing space for our workforce.
Upgraded fine ore bin and supersack of moly concentrate awaiting shipment
Ongoing upgrades at the mine that are nearing completion include increasing electrical power capacity, increased mine ventilation and improved compressed air systems. New mine equipment scheduled for delivery in the next few months includes a second mucker and two mine trucks.
During the maintenance period, the mill continued to operate, reprocessing tails from the pond and producing moly concentrates.
Crews pump tailings to the mill for reprocessing of any residual moly
This maintenance turnaround along with upgrades in mine infrastructure and new equipment will support Ashdown's push toward sustained production.
Sylvia vein samples showing dense mineralization
June 16, 2008
The mine has placed an order for two Atlas Copco Scooptrams (muckers), model number ST-2G, to be delivered shortly. The first is seen in the photos below at the Las Vegas equipment show last week, and has since been delivered to the mine. The second will arrive in a few weeks. The Scooptrams are used to remove and load ore from the working faces into trucks for delivery to the mill. They are designed to fit into the narrow drifts underground, and will replace older leased equipment. Additional heavy equipment is scheduled for purchase later this summer as part of the ramping up process.
GM Kent Aveson with new Scooptram at show


June 4, 2008
The following three maps show aerial, horizontal and oblique views of the underground workings of the Ashdown Mine development as of this date. Click on "Expand View" to enlarge.
Aerial View

Expand View
Horizontal View

Expand View
Oblique View

Expand View
December 6, 2007

The Ashdown mill continues moly production, with the filling of the last two sacks of the 12-sack shipment of Lot #16. Recovery rates exceeding 92% are reported, with head grades between 1-and-1.4 percent. 36 hours of planned maintenance was performed on the the crusher circuit, including hard-facing of the jaw crusher and liner plate rotation.
Work on the escapeway continues, with 45 foot advance from the first set inside the portal. Development work is on-going along the Sylvia drift, with over 80 feet advance along the drift, while ore production continues to feed the mill.
November 29, 2007

Ashdown's mine surveyor, Gail Doornek, is shown standing in the newly constructed portal that will lead to the secondary escapeway. Once excavation is completed early in 2008, this additonal mine access will be used for utilities and ventilation and provide an emergency escape route for the mining operations taking place 300 feet below. The escapeway, which was mandated by MSHA, is part of a comprehensive safety program initiated in late summer and nearing completion.

The design of the escapeway, which originated with the Ashdown mining staff, will provide multiple uses. Key among them is to create cross-ventilation underground, allowing the addition of heavy machinery in the mine workings which will meet air quality guidelines.
In addition to the portal development, a second tailings impoundment is being permitted adjacent to the mill, and construction of the Denio Junction Trailer Park continues with the installation of septic systems, grading of trailer pads and access roads. The Trailer Park will provide additional housing space for Ashdown employees once it is ready for occupation in 2008.
November 8, 2007
Moly shipment #14 was sold this week, and the mill is several sacks into shipment #15. Ron Johnson, an experienced metallurgist, has joined the staff to assist the expansion of production at the mill. Terry Perkins, the metallurgical QP (qualified person) for the 43-101 feasibility study team, made a 2-day visit to the mill and will be reporting on methodologies to continue to increase output.

Archaeological review of the secondary escapeway portal area has resulted in the granting of permission to proceed with the excavation of the escapeway from the surface. Crews will proceed following the completion of the necessary survey work. The new portal is faced up and ready to begin advance.
The Sylvia stopes, drift and scram are being prepared for production, including advancing #2 raise, installing slushers and tuggers. Ongoing rehab and utility work in the old and new Sylvia drift areas includes timber, bolts and shotcrete as needed. Ore continues to be mined in the Sylvia #2 raise, Sylvia stope and drift advance.
The price of moly oxide continues to firm up, at or around $33.00 per pound, with demand remaining strong domestically and overseas.
August 16, 2007

The mill continues to produce
cons. This supersack (above) is being filled with product generated
through reprocessing of tailings. A special reprocessing circuit was
designed and installed to be tested during the current relining of the ball
mill. The process is successfully recovering residual molybdenite
contained in the tailings impoundment, and represents one of several continuous
improvement programs underway at the mine.
A second improvement
program involves optimization of the crusher circuit (below), with replacement
of key parts to the jaw crusher and the addition of the magnet separator for
removing steel from the mill feed.

Below, mill technician
Mike Jones services the disk filter, inspecting filter cloths and vacuum pull.
Ashdown lab analysist, Edna
"Fastest-Gun-in-the-West" Read, is seen below assaying samples using the
handheld XRF gun. With this state-of-the-art equipment, the Ashdown Laboratory
is capable of realtime analysis of all mill and mine samples.
August 9, 2007

Conditioning
tank for staging tailings prior to reprocessing
In the photo, above, the dark green tank
is a 900-gallon conditioning tank being installed at the mill to retreat our
tails. Carpenter Mike Hatch is measuring height on the 1500-gallon containment
tank. All material pumped to and from the mill building and tails pond must be
in containment to meet state environmental standards.

Conveyor
system with electromagnet
This is the #2 conveyor
on our crushing system. It takes material from the jaw crusher up to the
vibrating deck screen. This summer, a large electromagnet was suspended over
the belt to remove trash steel from the ore. The magnet slides on the overhead
rail and the trash steel can be dumped directly into the trash drum.
In the photo below, Mill
Operator Tom Jones records measurements made by Mike Hatch from the handrail to
the trommel screen basket. This is during an unplanned maintenance period to
install a new mill liner, replace the trommel screen, install an automatic
lubrication system to the drive gear, and evaluate the mill trommel bearings.
The continuous-improvement program at the Ashdown mill is always striving for
increased efficiencies and higher productivity while maintaining a safe work
environment..

Tom and Mike
inspecting the ball mill
Below,
Tom is recording measurements taken from the trommel screen above the mill
discharge box during one of the maintenance periods. The mill discharge slurry
empties into this box and is pumped by the Gallagher pump (lower right) up to
the cyclone classifier.

Tom at the
Gallagher pump
Crews have just completed the construction of the new administration building,
located near the mill. This facility is awaiting final permitting by
Humboldt County. The new office will provide a better, more efficient work area
for management and consultants as the property transitions toward full
production and plans for expansion. The office will house the mill managerial
staff, safety and purchasing departments and the property General Manager.

New admin
building now ready for occupancy
August 7, 2007
Our men taking a break in the
new 4490 drift
During
July and August, the miners have been busy on a number of
development projects inside the Ashdown Mine. The 4480
drift, which supplied the mill with feed in June and July, has
been backfilled, allowing a second drift to be driven above it
on the 4490 level. The new drift is advancing well, with the
Sylvia vein continuing to provide excellent mineralization and
plenty of mill feed.

The Sylvia vein showing an intense band of molybdenite on
the 4490 level
A sand
plant was designed, built and put into operation in July, which
has expedited the backfilling of the 4480. The process of
backfilling involves the placement of rock in the drift,
followed by spraying a mixture of sand and cement to fill any
voids (see photos below). The sand is screened near the
mine and slurried into the drift for spraying into the voids.
This speeds up the process of filling and stabilizing the old
workings, and allows the miners to commence mining above the
backfilled areas.

Ashdown's newly completed sand
plant

Sand being injected into the
4480 drift

In addition to the mining work, underground crews are
constructing the secondary escapeway, which is currently
designed to follow the vein toward the surface. A raise
has been put in and is being extended toward the surface,
allowing removal of moly at the same time that the safety work
is being accomplished.

The secondary escape raise under construction; looking up
toward the vein
While crews are stockpiling mill feed, other crews have finished
extensive work to shore up and strengthen the main access
decline in anticiaption of winter conditions. The timber
work is completed resulting in strong backs and clean sills, and
easier equipment access to the workings. This work constitutes
preventative maintenance and is critical to the continued
expansion of mining capabilities at the working faces (see three
photos below).



Planning work for future expansion of mine operations is well
underway, under the direction of the Golden Phoenix Technical
Services Group(TSG). The archaeological survey/inventory
completed in 2006 as part of the BLM requirements for the
Environmental Assessment is being reviewed by a leading Nevada
historical archaeologist/permitting specialist to evaluate any
archaeological factors relating to the possible expansion of
mine facilities such as ventilations holes, adits, production
shafts and waste dumps. The archaeological evaluation will also
aid in site selection for development drilling to define
additional near-term mineable material and longer term expansion
of the Sylvia vein.
Under the direction of the TSG, project-wide
exploration will begin in late August with field testing of a
second Niton XRF analyzer which is expected to arrive within the
next few days. The XRF will be used for rapid geochemical
sampling of outcrops, roadcuts, and soils across the entire
Ashdown Project area. Field examination has shown that various
types of alteration related to moly-porphyry systems in other
districts in North America also occur on the Ashdown Project. Argillic
alteration of the quartz diorite is common in the hanging wall
of the Sylvia vein and occurs in outcrop in Vicksburg Canyon
immediately north of the mine. Potassic alteration occurs in the
form of biotite replacement of ferromagnesian minerals in the
quartz diorite across a large portion of the property. Potassic
alteration also occurs over a wide area as numerous, but subtle,
K-spar/quartz/biotite pegmatite dikes and veins. Quartz-sericite
alteration has been mapped in roadcuts and old mine workings.
The molybdenite currently being produced occurs primarily in
the quartz rich portions of the K-spar/quartz Sylvia vein.
The XRF sampling program is expected to aid in
defining zonation patterns while locating areas of anomalous
elemental moly and other related elements. The goal is to
identify the best possible targets to drill test for a potential
moly-porphyry deposit.

Another
look at the moly vein on 4490
The Ashdown Project LLC is also utilizing the TSG capabilities
to permit the expansion of the tails facility and mill expansion
needs. TSG met with State NDEP officials in preparation of the
required minor modification notice under 445A.416 of the
Nevada Revised Statutes and has collected soil samples as part
of the preliminary engineering requirements for the construction
of additional tails storage containment facilities. Dirt work on
this project is currently scheduled to begin in late August.
June 14, 2007
Craig Patrick, Golden Phoenix's newest
VP, joins the team to inspect Ashdown Mine.
CEO Dave
Caldwell (r) and Metallurgist Dave Tretbar at Ashdown

Moly supersack being loaded for
shipment

Supersack receiving dried cons

Same sack, different view

Mine tour

Next lot of Supersacks being stored



Tailings pond and outflow

Ball mill and flotation cells

Skimmer pushing moly froth into tray
Don Prahl at
Sylvia Vein, 4480 level

Dave Tretbar, underground
April 27, 2007
Drifting south along the Sylvia vein at the 4480
level, our crews encountered this mineralization. Initial in-house face
assays yielded 5.33% Mo, to be confirmed by outside assay. The molybdenite
(dark gray) runs over nine feet in width here, boardered by quartz. Pedro,
one of our miners, lends scale to the deposit.
April 17, 2007

This drill hole, No. 63699, was encountered by mining crews on the 4480 level,
while blasting and mucking for mill feed. Streaks of molybdenite can be
seen bordering the hole.
March 21, 2007

This cross sectional map
shows the current area of mining from a side elevation. The red lines
delineate the moly vein, illustrating the slope of the deposit within the
geologic container. Click on image to enlarge.
March 12, 2007
CEO Dave Caldwell and President Rob Martin attended the PDAC Mining Conference,
held the first week of March in Toronto. It was reportedly attended by
20,000 delegates from around the world, representing all aspects of mining,
exploration and finance.

Dave Caldwell, left,
hosting the GPXM Open House
Golden Phoenix
hosted an Open House and Exhibit during the conference, held at the Fairmont
Royal York Hotel. The Open House ran from 4 pm until well after
midnight on March 6th, and hosted well over 200 people. On exhibit
were the most recent mineral samples from the Ashdown Mine, as well as
current photos and maps of the project.

Moly samples were
the star attraction of the show
Many Golden Phoenix
shareholders took the time to drop by to view the moly samples and chat with
the Company officers. Samples of moly concentrate were given out, and
there was universal appreciation for the quality of the minerals on display.

Rob Martin, with
mining legend Frank Kruzich
The trip also
afforded Caldwell and Martin the opportunity to meet many of the key
organizations involved in the investment, finance and development of mining
projects, and to distribute information regarding GPXM's activities and
assets. The energy and excitement within the mining industry was
evident throughout the conference, during which Sprott Asset Management, a
major financial institution based in Toronto, announced the planned start of
a $75 million dollar Molybdenum Fund, which will allow investors a new
vehicle through which to participate in the resurgence of this strategic
metal.
February 22,
2007
The above photo shows the production from a one-week run of the mill.
Each Supersack contains approximately 3900 pounds of molybdenite, which
averages about 54% elemental Mo. The mill currently can process all
the ore the mine is producing, and further development work is being
performed to bring mineral production up to match the mill's 100-ton per day
capacity. This ramping process will take several months, and involves
increasing the working faces and numbers of miners.

Johnny pauses from
his stope work near the Sylvia Vein (in background). Crews continue to
mine the southern end of the sill drift to generate mill feed, while other
crews concentrate on driving a new raise into the high-grade section of the
vein. Once this development work is completed, additional crews can
start extraction of mineralization, which will, in turn, feed more material
to the mill and allow for gradual increase in output of saleable
concentrates. Until the mine is producing approximately 75 tons of
mill feed each and every day, the mill will be operated when sufficient mill
feed has been stockpiled to allow for continuous production of at least one
shipment, which averages about 48,000 pounds of bagged end-product.

Tom and Jason share
a smile as they finish up the week's mill run. Mill crews, including
operators and assay specialists, work round the clock to maintain the
"balance" in the flotation cells, monitor flow rates, test water chemistry,
and adjust reagents constantly. The training and learning that is
occuring will pay dividends when the mine production reaches the rate at
which the mill can operate full time throughout each month. By then,
the chemisty of the mineralization, which is unique for each ore body, can
be mastered, resulting in increasing efficiencies of production.
February 5, 2007
Work in the stopes
continues. Underground crews are advancing on the sill drift and getting
ready to develop the next raises and scrams to the south of the current
working face. Work is proceeding nicely. The focus is to add working
faces at the same level while mineralization is currently being removed.
Longer term, work is also proceeding on a drift to access the vein beneath
the current area. This work will take several months to complete.
In the meantime, mineralized material is being removed and stockpiled at the
mill, and some additions to the mill are being added this week. Initial
supersacks for a second shipment are already filled and the mill will resume
production shortly.
January 4,
2007

The Ashdown Mill
continues to make improvements to its equipement and processes. The
photo above shows the dryer unit with an upgraded ventilation system which
helps remove moisture from the cons. Below, Jason and Wayne stand in
front of the bagging system where cons from the dryer are cooled and packed
.

Other improvements
include the enclosure of the feed belt that connects the leaf filter,
located on the upper level of the mill building, to the dryer hopper in the
red container; and the compressor housing located at the back of the mill (2
photos below).


The tailings pond is
beginning to fill with the ramping operation of the mill and its cons
production.
In the mine, crews
are timbering the main stope leading to the face of the Sylvia vein and
driving drift to establish a second raise and series of working faces.
Seasonal water intrusion from above requires the crews to properly support
the workings as they mine. The Sylvia vein continues to produce
mineralized material showing very high grades. Mill feed production
will continue as development work is advanced. Development of
additional working faces is on-going and will occur in phases expected to
take several months to complete.
|